The Arcadia Zurich Road bridge replacement project has been completed.
Kevin Rooney, Wayne County’s superintendent of public works, said the new $1.72 million span over Ganargua Creek replaces a previous steel-girder structure, which had an open steel-grate deck. The new bridge is a single-span steel girder structure with a concrete deck, and the center pier was removed to improve water flow under the bridge.
Rooney said the bridge, which had been closed since May 1, was completed by Economy Paving of Cortland approximately two months ahead of schedule. The project engineer was CHA Engineers of Cortland.
Continue reading from The Finger Lakes Times
This content is brought to you by the FingerLakes1.com Team. Support our mission by visiting www.patreon.com/fl1 or learn how you send us your local content here.