Planned semiconductor plants, data centers and new energy projects are increasing pressure to expand upstate New York’s high-voltage electric grid, according to the Times Union.
Independent power developers want the state Public Service Commission to approve more transmission projects through competitions open to companies beyond existing utilities.
They argue competition could speed construction and lower costs, while National Grid says development should balance utility expertise with opportunities for outside bidders.
New York’s transmission network grew by a little more than 1% over the past decade, according to data from the state’s grid operator cited in the report.
The commission says it is identifying investments to meet rising demand and support clean-energy projects as utilities plan more than $4 billion in system improvements.
Make FL1 part of your day.
Local reporting. Useful updates. More ways to stay close to your community.
Go ad-free
Support independent local reporting and enjoy FL1 without display ads.
$4.99 / month
Become a member →Cancel anytime. Third-party media players may contain ads.Get the daily briefing
Start your morning with the headlines that matter across the Finger Lakes.
Find more FL1 on Google
Choose FingerLakes1.com as a preferred source to see more of our reporting in your Google news results.