Wayne County has put its name in for a role in New York’s nuclear expansion. While state officials sort out where new power plants could go, another group in Albany is working on who would pay for them.
A Nov. 18 white paper from Department of Public Service staff recommends building a program to support the revenue of new nuclear projects. It also says New York should leave room for other kinds of help, including early grants or loans, a state ownership stake and limited public sharing of construction overruns.
Those are staff recommendations in a Public Service Commission case. Regulators have yet to settle the funding terms for a particular project or say what such a commitment would cost a household.
What the state could take on
The state’s broader nuclear master plan lays out a goal of 5 gigawatts of new nuclear generating capacity. Added to the roughly 3.4 gigawatts already operating in New York, it would bring total nuclear capacity to about 8.4 gigawatts. A separate Power Authority initiative to develop at least 1 gigawatt would count toward that target.
For developers, the expense starts long before electricity is available to sell. A project must pay for site studies, design and licensing before it knows whether construction will go forward. The white paper recommends designing a funding program flexible enough to offer early financial support and protect project revenue once power is being produced.
Construction overruns are a separate question. The paper discusses putting the state behind the parties best able to control costs, so those parties would absorb the first overruns in any negotiated guarantee. Public exposure would depend on the final terms, including what losses qualify and whether New York takes an ownership stake.
Staff also recommend competitive negotiations in which bidders open their cost records to the state. Regulators would have to compare bids using consistent assumptions about cost, risk and the effect on customers. The paper leaves utility ownership to a separate review.
Where Wayne County fits
The New York Power Authority listed Wayne and Schuyler among counties that responded to its invitation for potential host communities. Wayne County’s interest received attention at the Rochester nuclear summit. The county already hosts the Ginna nuclear plant in the town of Ontario, and the Authority is looking at potential sites and partners for the upstate project.
For people paying electric bills, the financing case is where a broad state goal would begin to turn into specific obligations. The white paper also points to the possibility that large electricity users could sign long-term contracts to help support new generation. How much those buyers would cover and how much would fall to other customers depends on future agreements.
The staff’s next proposed step is a detailed implementation plan for commission review. It would spell out how bids are screened and evaluated and how customers’ costs would be measured before individual projects return to regulators for approval.
Make FL1 part of your day.
Local reporting. Useful updates. More ways to stay close to your community.
Go ad-free
Support independent local reporting and enjoy FL1 without display ads.
$4.99 / month
Become a member →Cancel anytime. Third-party media players may contain ads.Get the daily briefing
Start your morning with the headlines that matter across the Finger Lakes.
Find more FL1 on Google
Choose FingerLakes1.com as a preferred source to see more of our reporting in your Google news results.