West Bayard Street closes Monday in Seneca Falls: Here’s how it got to this point

Drivers will be detoured around West Bayard Street between Ovid and Bridge streets starting Nov. 30, with the Seneca Falls closure scheduled to last until May 1, 2027. The Town Board approved financing in September and awarded a $4.59 million construction contract in October to replace the stone culvert that forced the same stretch to close in 2019.

West Bayard Street closes Monday in Seneca Falls: Here’s how it got to this point

West Bayard Street will close Monday, Nov. 30, between Route 414 (Ovid Street) and Bridge Street in Seneca Falls so crews can replace the failing stone culvert beneath the road.

The stretch is scheduled to remain closed until May 1, 2027 and Town Supervisor Frank Schmitter said detour signs will be posted.

The closure returns drivers to the same stretch they spent nearly four months detouring around in 2019. The town claimed ownership of the culvert in 2024, and this fall the Town Board approved financing and unanimously awarded a $4.59 million construction contract to The L.C. Whitford Co. on Oct. 6.

The company was the lowest bidder among six.

Why the road closed in 2019

The culvert carries runoff from Center Street Pond, also known as Benton Pond, beneath West Bayard Street and neighboring properties to the Cayuga-Seneca Canal at Van Cleef Lake. The town dates the stone arch to the late 1800s. It became submerged when Van Cleef Lake was created, making it harder to inspect and maintain.

The town closed the road to through traffic on Aug. 29, 2019, after state inspectors found deterioration that raised concerns the roadway could collapse. Drivers initially detoured along Barker Street. Police moved the detour off neighborhood streets after residents raised safety concerns. The road reopened in December with a 6-ton weight limit and one lane in each direction. The interim plan eliminated the dedicated left-turn lane onto the Ovid Street bridge.

The culvert also causes problems for people who live nearby. The state Department of Environmental Conservation says sediment and debris regularly block the culvert and cause flooding. Then-Supervisor Michael Ferrara told the board in 2021 that when runoff from Sampson Creek backs up, the pond can overflow and flood homes near the bottom of Center Street.

How the town got to a construction contract

The state Canal Corp. maintained that the town was responsible for repairs. In February 2020, the board voted 5-0 to pursue a notice of claim to preserve its option to sue the agency. That summer, easement issues ruled out one repair option, and an underwater camera inspection failed to establish the arch’s condition.


The board rejected a Bridge NY grant resolution in 2021 after members questioned the proposed commitment of local funds. In January 2023, it unanimously backed a later application under a grant round that required no local match.

On April 2, 2024, the board unanimously claimed ownership of the culvert. Its resolution said the town had spent about 20 years trying to determine who owned it and that repairs were urgent. In June, the board backed a state water quality grant application that committed the town to a 25% local match. The state awarded Seneca Falls $1 million that December.

The board voted to lead an environmental review of the culvert work in October 2025 and authorized construction bidding in July 2026. The town bid the concrete sections separately because they take time to make and deliver. Fort Miller Co. received the separate $375,000 materials contract.

On Sept. 10, the board voted 4-0 to approve the environmental findings and authorize up to $6.5 million in borrowing. The borrowing authority and the $1 million state grant accounted for the $7.5 million project ceiling. The board awarded the general construction contract the following month.

Why the canal is being lowered

Crews will remove the submerged stone arch and install precast concrete sections 8 feet wide and 8 feet high. The construction contract also calls for rebuilding the roadway at the work site.

Schmitter said the town is working with Relevate Power to lower Van Cleef Lake and the nearby canal by an expected 12 to 14 feet so crews can reach the culvert. Relevate is using the drawdown to perform maintenance at its hydroelectric facility. The town expects culvert work to continue through April.

Seneca Falls police are asking people to stay off the exposed lake and canal beds, where deep mud, unstable ground and hidden debris can make footing dangerous.

Want to go ad-free?

Become an FL1 member and say goodbye to ads! Plus, you’ll be supporting a company rooted in the Finger Lakes for nearly 30 years.

$4.99 / month

Get ad-free access

Renews monthly. Cancel anytime through your account. Already contributing via Google? Sign in with your Google account and unlock ad-free access. Embedded YouTube videos and other third-party media players may still contain ads.

Start your day with FingerLakes1

Get the stories that matter from across the Finger Lakes, delivered to your inbox.

Your email will be added to our newsletter mailing list, hosted on Substack. Privacy policy